Skip to main contentSkip to solution

When they work alone, BB needs 25%25 \% more time to finish a job than AA does. They two finish the job in 1313 days in the following manner: AA works alone till half the job is done, then AA and BB work together for four days, and finally BB works alone to complete the remaining 5%5\% of the job. In how many days can BB alone finish the entire job?

Solution

✅ Correct Option: 2

Let's break down what happens in this 13-day work sequence:

A works alone until half the job is done

A and B work together for 4 days

B works alone to complete the remaining 5% of the job

We need to find how long B takes to finish the entire job alone.


Let's say A can finish the entire job alone in a days.

Since B needs 25% more time than A:

B's time = A's time + 25% of A's time

B's time = a + 0.25a = 1.25a = 5a4\dfrac{5a}{4} days

Work Rates (portion of job completed per day):

A's rate = 1a\dfrac{1}{a} jobs per day

B's rate = 15a4=45a\dfrac{1}{\dfrac{5a}{4}} = \dfrac{4}{5a} jobs per day


Here's the key insight: What portion of the job do A and B complete together?

A completes: 50% of the job alone

B completes: 5% of the job alone

A and B together complete: 100% - 50% - 5% = 45% of the job

So A and B working together for 4 days complete 45100=920\dfrac{45}{100} = \dfrac{9}{20} of the job.


When A and B work together for 4 days:

Combined work rate × Time = Work completed

4×(1a+45a)=9204 \times \left(\dfrac{1}{a} + \dfrac{4}{5a}\right) = \dfrac{9}{20}


Let's simplify the left side:

4×(1a+45a)=4×(55a+45a)4 \times \left(\dfrac{1}{a} + \dfrac{4}{5a}\right) = 4 \times \left(\dfrac{5}{5a} + \dfrac{4}{5a}\right)

=4×95a=365a= 4 \times \dfrac{9}{5a} = \dfrac{36}{5a}

So our equation becomes:

365a=920\dfrac{36}{5a} = \dfrac{9}{20}

Cross-multiplying:

36×20=9×5a36 \times 20 = 9 \times 5a

720=45a720 = 45a

a=72045=16a = \dfrac{720}{45} = 16


A takes 16 days to complete the job alone.

B takes 5a4=5×164=804=20\dfrac{5a}{4} = \dfrac{5 \times 16}{4} = \dfrac{80}{4} = 20 days to complete the job alone.


B alone can finish the entire job in 20 days.


In work and time problems, always identify what portion of work each person/combination completes. This helps you set up the correct equations without getting confused by the different working arrangements.

Keyboard Shortcuts

  • Left arrow: Previous question
  • Right arrow: Next question
  • S key: Jump to solution
  • Q key: Jump to question